Sprint Plan
Sprint scope and timeline for the Telemetry Hub work cycle. See Overview for goals, approach, and current state of play.
Sprint 1 — 2026-04-21 → 2026-04-28
Scope for Sprint 1:
- Overview/Approach updates:
- Adoption of "Telemetry Hub" as the formal name for this component
- Responsibility Assignment between EBU and HNR.
- State of Play updates:
- Platform capabilities
- Telemetry inventory
- Development priorities
- Telemetry section on the testbed website, with:
- Overview page
- Shared Dashboards placeholder page
- Telemetry Hub architecture page
- Telemetry Status section on the site
- Initial Dashboard
- Grafana Access
- Access for Kris
- Access for Hemini
- Sprint Planning
- Definied scope for Sprint 2 and Sprint 3.
Sprint 2 — 2026-04-29 → 2026-05-05
This is a short sprint due to the May 4th bank holiday and the EBU Horizons 2026 event on May 5th and 6th.
Scope to be agreed at the Sprint 1 close. Candidates are:
- Expanding collection points beyond CDN logs.
- Filling out metric specifications for player, uplink, downlink, origin, and CDN components.
Sprint 3 — 2026-05-06 → 2026-05-12
Scope to be agreed at the Sprint 1 close. Candidates are:
- ???