Sprint Plan

Sprint scope and timeline for the Telemetry Hub work cycle. See Overview for goals, approach, and current state of play.


Sprint 1 — 2026-04-21 → 2026-04-28

Scope for Sprint 1:

  • Overview/Approach updates:
    • Adoption of "Telemetry Hub" as the formal name for this component
    • Responsibility Assignment between EBU and HNR.
  • State of Play updates:
    • Platform capabilities
    • Telemetry inventory
    • Development priorities
  • Telemetry section on the testbed website, with:
    • Overview page
    • Shared Dashboards placeholder page
    • Telemetry Hub architecture page
  • Telemetry Status section on the site
    • Initial Dashboard
  • Grafana Access
    • Access for Kris
    • Access for Hemini
  • Sprint Planning
    • Definied scope for Sprint 2 and Sprint 3.

Sprint 2 — 2026-04-29 → 2026-05-05

This is a short sprint due to the May 4th bank holiday and the EBU Horizons 2026 event on May 5th and 6th.

Scope to be agreed at the Sprint 1 close. Candidates are:

  • Expanding collection points beyond CDN logs.
  • Filling out metric specifications for player, uplink, downlink, origin, and CDN components.

Sprint 3 — 2026-05-06 → 2026-05-12

Scope to be agreed at the Sprint 1 close. Candidates are:

  • ???